46.
Which option is not a responsibility of the person designated to manage the continuity planning process?
  • A.
    Providing information and direction to senior management staff
  • B.
    Providing stress mitigation programs to employees after an asset loss event
  • C.
    Analyzing and identifying all critical business functions
  • D.
    Coordinating and planning integration among business units
  • Answer & Explanation
  • Report
Answer : [B]
Explanation :
Stress reduction programs and other employee benefi t programs is usually the responsibility of the human resources department. Options A, C, and D describe responsibilities of the person designated to manage the continuity planning process.
Report
Name Email  
47.
Which disaster recovery/emergency management plan testing type is considered the most cost-effective and efficient way to identify areas of overlap in the plan before conducting a more demanding training exercise?
  • A.
    Full failover test
  • B.
    Structured walk-through test
  • C.
    Tabletop exercise
  • D.
    Bullet point test
  • Answer & Explanation
  • Report
Answer : [B]
Explanation :
This plan is both cost effective and effi cient. Option A is a very expensive test. Although they are types of tests, options C and D may be used to update information only.
Report
Name Email  
48.
Which of the following options best describes a cold site?
  • A.
    An alternate processing facility with established electrical wiring and HVAC but no data processing hardware
  • B.
    An alternate processing facility with most data processing hardware and software installed, which can be operational within a matter of hours to a few days
  • C.
    An alternate processing facility that has all hardware and software installed and is mirrored with the original site and can be operational within a very short period of him him him him time
  • D.
    A mobile trailer with portable generators and air-conditioning
  • Answer & Explanation
  • Report
Answer : [A]
Explanation :
A cold site does not have hardware. Options B, C, and D describe warm and hot sites.
Report
Name Email  
49.
Which of the following statements is an incorrect description of a control?
  • A.
    Detective controls monitor for attacks and instigate preventative or corrective controls.
  • B.
    Controls reduce the possibility that vulnerabilities will be attacked.
  • C.
    The effect of an attack is reduced through the use of controls
  • D.
    Restorative controls reduce the likelihood of a deliberate attack.
  • Answer & Explanation
  • Report
Answer : [D]
Explanation :
Corrective controls stop an activity once it has begun. Options A, B, and C describe types of controls.
Report
Name Email  
50.
Which of the five disaster recovery testing types creates the most risk for the enterprise?
  • A.
    Simulation
  • B.
    Parallel
  • C.
    Structured walk-through
  • D.
    Full interruption
  • Answer & Explanation
  • Report
Answer : [D]
Explanation :
A full irruption test provides the most risk for the enterprise. Options A, B, and C are other types of test scenarios