36.
What agenda items should you cover during the kick - off meeting? (Choose all that apply.)
  • A.
    Building construction
  • B.
    Explanation of survey process
  • C.
    DAreas of difficult AP installation
  • D.
    Review of customer requirements
  • Answer & Explanation
  • Report
Answer : [B, D]
Explanation :
Key project stakeholders need to be made familiar with the process involved in site surveys, including the typical challenges that commonly occur that can compromise the integrity of the final design. Customer requirements should also be reviewed with the customer.
Report
Name Email  
37.
Which item does not belong apply to the walkthrough?
  • A.
    Looking for areas of high user density
  • B.
    Accessing all areas to confirm line of sight
  • C.
    Exploring areas of challenging construction
  • D.
    Identifying IDF/MDF locations
  • Answer & Explanation
  • Report
Answer : [B]
Explanation :
It is usually not possible to access all areas where radios will need to be installed to confi rm line of sight. The walkthrough should document the equipment and tools that will be necessary to perform this work, along with planning for alternative locations.
Report
Name Email  
38.
During a customer walkthrough you notice an area of the CAD drawing where it is not accurate. What next step should you take?
  • A.
    Redraw the portions of the map that have changed.
  • B.
    Request the survey team to do their best to walk where necessary and use the references on the map.
  • C.
    Do not survey that area.
  • D.
    Request a new version.
  • Answer & Explanation
  • Report
Answer : [D]
Explanation :
It is best to not attempt to augment a version of the customer ’ s map as the details may not be accurate. You should request from the customer an updated map and require that it be accurate in order to obtain higher - quality results. If one does not exist, the customer needs to understand the potential impact on results.
Report
Name Email  
39.
For what types of systems should you request read - only access to in order to perform an analysis of the customer ’ s existing infrastructure? (Choose all that apply.)
  • A.
    Routers
  • B.
    Switches
  • C.
    Clients
  • D.
    RADIUS
  • E.
    Active Directory
  • Answer & Explanation
  • Report
Answer : [A, B]
Explanation :
Routers and switches are the primary devices of focus when performing an analysis of the customer environment. For other systems, it may be important to obtain proof of how they are confi gured.
Report
Name Email  
40.
When working with a military organization, what type of compliance requirement might you expect?
  • A.
    Strong security policy
  • B.
    FIPS 140 - 2 encryption
  • C.
    Security clearance
  • D.
    36 dBm
  • E.
    Background check
  • Answer & Explanation
  • Report
Answer : [C]
Explanation :
Many military organizations require a heightened level of security clearance.