What preexisting document should be reviewed during the kick - off meeting with the customer?
  • A.
    SOW
  • B.
    Interference report
  • C.
    MSA
  • D.
    Acceptance criteria
  • Answer & Explanation
  • Report
Answer : [A]
Explanation :
Kick - off meetings happen after the contract signing, and the statement of work (SOW) is an outcome of the contractual process. This document should be reviewed during the kick- off meeting with the customer to resolve any discrepancies.
Report
Name Email  
32.
When a walkthrough is scheduled with the customer, what parties should be invited to the meeting?
  • A.
    IT team
  • B.
    End users
  • C.
    Project sponsor
  • D.
    Facility
  • E.
    Project stakeholders
  • Answer & Explanation
  • Report
Answer : [E]
Explanation :
Any project stakeholder is the most correct answer. Anybody who will have a role in the project should be invited to the kick- off meeting for at least the portion that pertains to them.
Report
Name Email  
33.
During the walkthrough process, you need to be looking for which of the following? (Choose all that apply.)
  • A.
    Areas that will require specialized tools
  • B.
    Potential sources of interference
  • C.
    Areas that require advanced scheduling
  • D.
    Antenna height
  • E.
    Areas of high user density
  • Answer & Explanation
  • Report
Answer : [A, B, C, D]
Explanation :
Pay careful attention to all these areas during the walkthrough.
Report
Name Email  
34.
An MSA commonly addresses at least which two legal categories?
  • A.
    Nondisclosure agreement
  • B.
    Hold harmless
  • C.
    Indemnity clause
  • D.
    Intellectual property protection
  • Answer & Explanation
  • Report
Answer : [A, B]
Explanation :
A master services agreement (MSA) commonly addresses a hold harmless agreement and an NDA.
Report
Name Email  
35.
What important document should be obtained prior to the walkthrough and confirmed for accuracy?
  • A.
    SOW
  • B.
    LAN design
  • C.
    NDA
  • D.
    CAD drawing
  • Answer & Explanation
  • Report
Answer : [D]
Explanation :
One of the most important documents is the CAD drawing. This document needs to be reviewed to ensure it is accurate during the walkthrough.