- Home
- General Aptitude
- Chain Rule
1.
Running at the same constant rate, 6 identical machines can produce a total of 270 bottles per minute. At this rate, how many bottles could 10 such machines produce in 4 minutes?
- A.648
- C.2700
- B.1800
- D.10800
- Answer & Explanation
- Report
Answer : [B]
Explanation :
Explanation :
Let the required number of bottles be Rs. x. | |||||||||
More machines, More bottles (Direct Proportion) | |||||||||
More minutes, More bottles (Direct Proportion) | |||||||||
|
|||||||||
|
|||||||||
|
|||||||||
|
|||||||||
2.
If 5 men or 9 women can do a piece of work in 19 days, then in how many days will 3 men and 6 women do the same work?
- A.12
- C.18
- B.15
- D.21
- Answer & Explanation
- Report
Answer : [B]
Explanation :
Explanation :
Let the required number of days be x. | |||||||||||||||||||||||
|
|||||||||||||||||||||||
|
|||||||||||||||||||||||
Now, More women, Less days (Indirect Proportion) | |||||||||||||||||||||||
|
|||||||||||||||||||||||
3.
An industrial loom weaves 0.128 metres of cloth every second. Approximately, how many seconds will it take for the loom to weave 25 metres of cloth?
- A.178
- C.204
- B.195
- D.488
- Answer & Explanation
- Report
Answer : [B]
Explanation :
Explanation :
Let the required time be x seconds. Then, More metres, more time ( Direct Proportion) | |||||||||||||
|
|||||||||||||
|
|||||||||||||
|
|||||||||||||
|
|||||||||||||
|
|||||||||||||
4.
|
|||||||
of additional persons. Working 8 hours per day, required to complete the remaining work in 20 days, is |
- A.675
- C.250
- B.275
- D.225
- Answer & Explanation
- Report
Answer : [B]
Explanation :
Explanation :
Let the number of persons completing the work in 20 days be x. | |||||||||||||||||||
|
|||||||||||||||||||
Less hours per day, More men required (Indirect Proportion) | |||||||||||||||||||
More work, More men required (Direction Proportion) | |||||||||||||||||||
More days, Less men required (Indirect Proportion) | |||||||||||||||||||
|
|||||||||||||||||||
|
|||||||||||||||||||
|
|||||||||||||||||||
|
|||||||||||||||||||
|
|||||||||||||||||||
5.
30 labourers, working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers to finish the same piece of work in 30 days, will be:
- A.15
- C.22
- B.21
- D.25
- Answer & Explanation
- Report
Answer : [B]
Explanation :
Explanation :
Let the required number of laourers be x. Then, | ||||||||||
Less working hrs / day, More Labourers (Indirect Proportion) | ||||||||||
More days, Less Labourers (Indirect Proportion) | ||||||||||
|
||||||||||
|
||||||||||
|
||||||||||
|
||||||||||